The PDF version pdf file
Display Related Directives to this directive.
Display Reference Documents to this directive.

U.S. DEPARTMENT OF ENERGY	ORDER

Washington, D.C. 	DOE O 413.3A

		Approved: 7-28-06

Chg 1: 11-17-08

		

SUBJECT:	PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF 
		CAPITAL ASSETS

1.	OBJECTIVES.

	a.	To provide the Department of Energy (DOE), including the National Nuclear 
		Security Administration, with project management direction for the acquisition 
		of capital assets with the goal of delivering projects on schedule, within budget, 
		and fully capable of meeting mission performance, safeguards and security, and 
		environmental, safety, and health standards.

	b.	To implement Office of Management and Budget Circulars A-11 Part 7, A-123, 
		A-127, and A-130.

	c.	To implement DOE P 413.1, Program and Project Management Policy for the 
		Planning, Programming, Budgeting, and Acquisition of Capital Assets, 
		dated 6-10-00. 

2.	CANCELLATIONS. 

	DOE O 413.3, Program and Project Management for the Acquisition of Capital Assets, 
	dated 10-13-00. Cancellation of an Order does not by itself modify or otherwise affect 
	any contractual obligation to comply with the Order. Contractor Requirements 
	Documents containing directive requirements that have been applied to a contract 
	remain in effect until the contract is modified to eliminate or replace requirements from 
	canceled directives. 

	Further, DOE O 413.3 cancels Chapters 1 through 3 of DOE M 413.3-1, Project 
	Management for the Acquisition of Capital Assets, dated 3-28-03, and takes precedence 
	over the Manual where conflicts exist.

3.	APPLICABILITY.

	a.	DOE Elements. 

		The requirements identified in this Order are mandatory for all DOE Elements 
		(unless identified in the exclusions paragraph), including the National Nuclear 
		Security Administration, for all capital asset acquisition projects having a Total 
		Project Cost or Environmental Management Total Project Cost for Clean-Up 
		Projects greater than or equal to $20 Million (M). 

		The principles as set forth in this Order and Project Assessment and Reporting 
		System reporting requirements apply to all projects with a Total Project Cost or 
		Environmental Management Total Project Cost greater than or equal to $5M.

		While all requirements are to be addressed, the approach to meeting the 
		requirements should be tailored consistent with the risk, complexity, visibility, 
		cost, safety, security, and schedule of the project. All programs and projects 
		shall comply with applicable laws, regulations, Executive orders, and DOE 
		directives.

		The Under Secretary, National Nuclear Security Administration will assure that 
		National Nuclear Security Administration employees and contractors comply 
		with their respective responsibilities under this directive. Any reference in this 
		Order to the Program Secretarial Officer is also applicable to the Deputy 
		Administrator/Associate Administrators, National Nuclear Security 
		Administration. Nothing in this Order will be construed to interfere with the 
		NNSA Administrator’s authority under Section 3212 (d) of Public Law (P.L.) 
		106-65 to establish Administration-specific policies, unless disapproved by the 
		Secretary.

	b.	DOE Contractors. 

		The Contractor Requirements Document, Attachment 2, identifies specific 
		requirements of this Order that will apply to management and operating and 
		other prime contracts that include the Contractor Requirements Document. The 
		Contractor Requirements Document must be included in contracts making the 
		contractor responsible for project execution at DOE-owned or -leased facilities. 

	c.	Exclusions. 

		(1)	Naval Reactors, National Nuclear Security Administration. In accordance 
			with the responsibilities and authorities assigned by Executive Order 
			(E.O.) 12344 and to ensure consistency throughout the joint Navy and 
			DOE organization of the Naval Nuclear Propulsion Program, the Director 
			of the Naval Nuclear Propulsion Program will implement and oversee all 
			requirements and practices pertaining to this DOE Order for activities 
			under the Director’s cognizance.

		(2)	Bonneville Power Administration is excluded in accordance with 
			Secretarial Delegation Order 00-033.00A, dated 09/27/2002. 

		(3)	Financial Assistance awards (grants and cooperative agreements), which 
			are covered under 10 CFR 600, are excluded.

4.	IMPLEMENTATION. For the design and construction of Hazard Category 1, 2, and 3 
	nuclear facilities, or for projects including major modifications thereto (as defined in 10 
	CFR Part 830), the requirements in DOE-STD-1189, as amended, must be fully 
	implemented. 

5.	REQUIREMENTS. Topics addressed in the following paragraphs are accessible through 
	links in the following topic list.

	a.	Project Management Principles					4

	b.	DOE Acquisition Management System				4

	c.	Project Phases							5

		(1)	Initiation Phase.						5

		(2)	Definition Phase.						5
		
		(3)	Execution Phase.						6

		(4)	Transition/Closeout Phase.					7

	d.	Critical Decisions.							7

		(1)	CD-0, Approve Mission Need.				7
		
		(2)	CD-1, Approve Alternative Selection and Cost Range.		8
		
		(3)	CD-2, Approve Performance Baseline.			8
		
		(4)	CD-3, Approve Start of Construction.			9
		
		(5)	CD-4, Approve Start of Operations or Project Completion.	9

	e.	Critical Decision Approval Authority and Thresholds.			9

	f.	Tailoring.							17

	g.	Application of Critical Decisions to Unique Projects.			18

		(1)	Environmental Management Cleanup Projects.		18
		
		(2)	Information Technology Projects.				18
		
		(3)	Design-Build Projects.					19
		
		(4)	Projects Requiring Long-lead Procurement.			20
		
		(5)	Projects Authorized by the Annual National Defense 
			Authorization Acts					20

	h.	Reviews.	21

		(1)	CD-0.							21
		
		(2)	CD-1.							22

		(3)	CD-2.							22

		(4)	CD-3.							23

		(5)	CD-4.							23

	i.	Baseline Management.						23

	j.	Project Reporting and Progress Reviews.				25

	k.	Topical Areas.							26

		(1)	Acquisition Strategy.					26
		
		(2)	Conceptual Design/Conceptual Design Report.		26

		(3)	Earned Value Management System.				27

		(4)	Environment, Safety and Health Documentation Development.	27

		(5)	Integrated Project Team.					29

		(6)	Integrated Safety Management System.			29

		(7)	Key Performance Parameters.				31

		(8)	Performance Baseline.					31

		(9)	Project Execution Plan.					31

		(10)	Quality Assurance.					32

		(11)	Risk Management.						32

		(12)	Safeguards and Security.					32


	a.	Project Management Principles. 

		Fundamental project management principles provide a framework for successful 
		project execution. The requirements set forth in this Order are established to 
		ensure adherence to the following principles: 
		
		(1)	Line management accountability

		(2)	Sound disciplined up-front planning

		(3)	Development and implementation of sound acquisition strategies

		(4)	Well-defined and managed performance baselines

		(5)	Effective project management systems (e.g., quality assurance, risk 
			management, change control, performance management)

		(6)	Implementation of an Integrated Safety Management System

		(7)	Effective communication among all project stakeholders

	b.	DOE Acquisition Management System. 

		The DOE Acquisition Management System establishes principles and processes 
		to translate user needs and technological opportunities into reliable and 
		sustainable facilities, systems, and assets that provide a required mission 
		capability. The system is organized by project phases and Critical Decisions 
		(CDs), which represent a logical maturing of broadly stated mission needs into 
		well-defined requirements resulting in operationally effective, suitable, and 
		affordable facilities, systems, and other products. Tailoring is an essential 
		element of the acquisition process and shall be applied to all projects, although 
		the greatest amount of tailoring will typically be applied to smaller, low-risk, 
		and non-complex projects. Figure 1 illustrates a typical implementation of the 
		DOE Acquisition Management System for Line Item Projects. 

		Figure 1. Typical DOE Acquisition Management System for Line Item Projects.

	c.	Project Phases. 

		(1)	Initiation Phase. 

			During this phase, preconceptual planning activities focus on the 
			Program’s strategic goals and objectives. User needs are analyzed for 
			consistency with the Department’s strategic plan, Congressional 
			direction, administration initiatives, and political and legal issues. One 
			outcome of the analysis could be a determination that a user need exists 
			that cannot be met through other than material means. This outcome 
			leads to the development and approval of a Mission Need Statement. The 
			information developed during this phase also provides the basis for the 
			Project Engineering and Design budget request when preliminary design 
			activities are planned. 

		(2)	Definition Phase. 

			Upon approval of mission need, the project enters the Definition Phase 
			where alternative concepts, based on user requirements, risks, costs, and 
			other constraints, are analyzed to arrive at a recommended alternative. 
			This is accomplished using Systems Engineering and other techniques 
			and tools such as alternatives analysis and Value Management/Value 
			Engineering. This ensures the recommended alternative provides the 
			essential functions and capability at optimum life cycle cost, consistent 
			with required performance, scope, schedule, cost, security, and 
			Environment, Safety and Health considerations. During this phase, the 
			required Value Management assessment is completed, and more detailed 
			planning is accomplished which further defines required capabilities. The 
			products produced by this planning provide the detail necessary to 
			develop a range of estimates for the project cost and schedule.

		(3)	Execution Phase. 
		
			Following the Definition Phase, preliminary design activities mark the 
			beginning of the Execution Phase. Systems Engineering continues to 
			balance requirements, cost, schedule, and other factors to optimize the 
			design, cost, and capabilities that satisfy the mission need. Engineering 
			and design continue until the project has a sufficiently mature design 
			that can be implemented successfully within a firm Performance 
			Baseline. 

			During this phase, the initial design concepts and the preliminary design 
			are developed into detailed and final designs and plans. These plans are 
			used to procure or manufacture components, fabricate subsystems, or 
			construct, remediate, decommission or demolish facilities. Major 
			activities in this phase include:

			(a)	Establishing Performance Measurement Baselines and 
				implementing change control procedures;

			(b)	Satisfying environmental and safety requirements;

			(c)	Obtaining approved National Environmental Policy Act 
				documentation, if required, prior to the start of detail or final 
				design;

			(d)	Continuing to refine and optimize cost estimates, schedules, and 
				designs; and

			(e)	Approving the final design for procurement and implementation. 

			(f)	Identifying and addressing security concerns.

			Execution comprises the longest and most costly phase of a project. 
			Value Management and Value Engineering are implemented throughout 
			the project Execution Phase to ensure the most effective solutions are 
			implemented. 

			If the delivery method is Design-Build versus Design-Bid-Build and a 
			single contract is awarded for both design and construction, it may be 
			necessary to tailor the project’s execution process to allow the project 
			team to propose cost-effective innovative approaches that reduce project 
			duration and cost.

		(4)	Transition/Closeout Phase. 

			When the project nears completion and has progressed into formal 
			transition and commissioning, which generally includes final testing, 
			inspection, and documentation, the project is prepared for operation, 
			long-term care, or closeout. The nature of the transition and its timing 
			depends on the type of project and the requirements that were identified 
			subsequent to the mission need. 

	d.	Critical Decisions. 

		The five Critical Decisions are major milestones approved by the Secretarial 
		Acquisition Executive or Acquisition Executive that establish the mission need, 
		recommended alternative, Acquisition Strategy, the Performance Baseline, and 
		other essential elements required to ensure that the project meets applicable 
		mission, design, security, and safety requirements. Each Critical Decision marks 
		an increase in commitment of resources by the Department and requires 
		successful completion of the preceding phase or Critical Decision. Collectively, 
		the Critical Decisions affirm the following:

			•	There is a need that cannot be met through other than material means;

			•	The selected alternative and approach is the optimum solution;

			•	Definitive scope, schedule and cost baselines have been developed;

			•	The project is ready for implementation; and

			•	The project is ready for turnover or transition to operations.

			The amount of time between decisions will vary. Projects may quickly proceed 
			through the early Critical Decisions due to a lack of complexity, the presence of 
			constraints that reduce available alternatives, or the absence of significant 
			technology and developmental requirements. In these cases, more than one 
			Critical Decision may be approved simultaneously. Conversely, there may be a 
			need to split a Critical Decision. 

		(1)	CD-0, Approve Mission Need. 

			The Initiation Phase begins with the identification of a mission-related 
			need. A Program identifies a credible performance gap between its 
			current capabilities and capacities and those required to achieve the goals 
			articulated in its strategic plan and/or in the DOE Target Enterprise 
			Architecture for IT capital asset projects.. A Mission Need Statement is 
			the translation of this gap into functional requirements that cannot be met 
			through other than material means. It should describe the general 
			parameters of the project, how it fits within the mission of the Program, 
			and why it is critical to the overall accomplishment of the Department 
			mission, including the benefits to be realized. The mission need is 
			independent of a particular solution, and should not be defined by 
			equipment, facility, technological solution, or physical end-item. This 
			approach allows the Program the flexibility to explore a variety of 
			solutions and not limit potential solutions. Approval of CD-0 formally 
			establishes a project and begins the process of conceptual planning and 
			design used to develop alternative concepts and functional requirements. 
			Additionally, CD-0 approval allows the Program to request Project 
			Engineering and Design funds for use in preliminary design, final design, 
			and baseline development.
	
		(2)	CD-1, Approve Alternative Selection and Cost Range. 

			CD-1 approval marks the completion of the project Definition Phase, 
			during which time the conceptual design is developed. This is an iterative 
			process to define, analyze, and refine project concepts and alternatives. 
			This process uses a systems methodology that integrates requirements 
			analysis, risk identification and analysis, acquisition strategies, and 
			concept exploration to evolve a cost-effective, preferred solution to meet 
			a mission need. Approval of CD-1 provides the authorization to begin the 
			project Execution Phase and allows Project Engineering and Design 
			funds to be used. For design-build projects, Project Engineering and 
			Design funds may be used to develop a Statement of Work/Request for 
			Proposal. Additionally, long-lead procurements may be approved during 
			this phase, provided National Environmental Policy Act documentation is 
			prepared, where applicable.

		(3)	CD-2, Approve Performance Baseline. 

			Completion of preliminary design is the first major milestone in the 
			project Execution Phase. Preliminary design is complete when it provides 
			sufficient information for development of the Performance Baseline in 
			support of CD-2. The Performance Baseline is developed based on a 
			mature design, a well-defined and documented scope, a resource-loaded 
			detailed schedule, a definitive cost estimate, and defined Key 
			Performance Parameters. Approval of CD-2 authorizes submission of a 
			budget request for the total project cost. For projects with design periods 
			less than 18 months, a budget request may be submitted prior to CD-2 
			approval as part of tailoring.

		(4)	CD-3, Approve Start of Construction. 

			With design and engineering essentially complete, a final design review 
			performed, all environmental and safety criteria met, and all security 
			concerns addressed, the project is ready to begin construction, 
			implementation, procurement, or fabrication. CD-3 provides 
			authorization to complete all procurement and construction and/or 
			implementation activities and initiate all acceptance and turnover 
			activities. Approval of CD-3 authorizes the project to commit all the 
			resources necessary, within the funds provided, to execute the project.
		
		(5)	CD-4, Approve Start of Operations or Project Completion. 

			CD-4 marks the achievement of the completion criteria defined in the 
			Project Execution Plan and approval of transition to operations. This 
			decision is predicated on the readiness to operate and/or maintain the 
			system, facility, or capability. Transition and turnover does not 
			necessarily terminate all project activity. Rather, it marks a point at 
			which the operations organizations assume responsibility for operation 
			and maintenance. All projects must have a project transition/closeout 
			plan that clearly defines the basis for attaining initial or full operating 
			capability or meeting performance criteria as required for project 
			closeout, as applicable. The key attributes in turnover are the 
			Government’s readiness to operate, the ability to assume operational 
			responsibility, and the acceptance of the asset.
	
	e.	Critical Decision Approval Authority and Thresholds. 

		The Deputy Secretary serves as the Secretarial Acquisition Executive for the 
		Department and promulgates Department-wide policy and direction. The Critical 
		Decision authorities, thresholds and delegations are identified in Table 1.

			•	Major System Projects. 

			Projects with a Total Project Cost greater than or equal to $750M or 
			Environmental Management Clean-Up Projects with an Environmental 
			Management Total Project Cost of $1B are Major System Projects. All 
			Major System Project Critical Decisions must be proposed by the 
			appropriate Program Secretarial Officer and approved by the Deputy 
			Secretary as DOE’s designated Secretarial Acquisition Executive before 
			proceeding to the next project phase or Critical Decision.

			•	Non-Major System Projects. 

			Projects with a Total Project Cost less than $750M or Environmental 
			Management Clean-Up Projects with an Environmental Management 
			Total Project Cost less than $1B are Non-Major System Projects. The 
			designated Acquisition Executive must approve all Non-Major System 
			Project Critical Decisions, except for CD-0, which cannot be delegated 
			below the Program Secretarial Officer.

		The Chief Information Officer will function as the Acquisition Executive for all 
		Information Technology capital assets deemed by the Deputy Secretary to be 
		Department-wide with total project Development, Modernization, and 
		Enhancement funding of $20 M and greater, and Development, Modernization, 
		and Enhancement funding of $5 M or more in Current year or Budget year. 
		Departmental Information Technology capital assets will be defined by the 
		Deputy Secretary and are characterized by: 1) their widespread and continuous 
		use among multiple Departmental organizational units; 2) their vital importance 
		to accomplishing the Department’s business functions; and 3) their special 
		importance to agency senior management.

		Table 1. Critical Decision Authority Thresholds
		SEE THE TABLE IN THE PDF

		Table 2 provides a list of mandatory prerequisites to obtain Secretarial 
		Acquisition Executive/Acquisition Executive approval for each Critical 
		Decision. Additionally, Table 2 provides approval authorities. Where no 
		approval authorities are noted, authorities are established through other 
		directives or the Programs (e.g., Functions and Requirements Assignment 
		Matrix). Any reference in this Table to the Program Secretarial Officer is also 
		applicable to the Deputy Administrator/Associate Administrators, National 
		Nuclear Security Administration. Appropriate to project risk, size, and 
		complexity, requirements are expected to be tailored to the project and be 
		approved by the Secretarial Acquisition Executive/Acquisition Executive. 
		Projects must utilize the five Critical Decisions; however, in unique 
		circumstances, Critical Decisions may be combined or split by appropriate 
		tailoring. The tailoring approach must have a rational, clear, and documented 
		basis. DOE-STD-1189, as amended,- provides implementation guidance for 
		Hazard Category 1, 2, and 3 nuclear facilities safety requirements.

		Table 2. Critical Decision Requirements
		SEE THE TABLE IN THE PDF

	f.	Tailoring. 

		Tailoring is an essential element of the acquisition process and must be 
		appropriate considering the risk, complexity, visibility, cost, safety, security, 
		and schedule of the project. The requirements of this Order are to be applied on a 
		tailored basis as appropriate to the project. Tailoring is subject to the 
		Acquisition Executive’s approval and is identified prior to the impacted Critical 
		Decision and approved as early as possible starting at CD-0, if appropriate. In 
		the Tailoring Strategy or the Project Execution Plan, the Federal Project Director 
		will identify those areas a project plans to tailor and an explanation/discussion 
		of each tailored area. The Project Execution Plan/Tailoring Strategy is updated prior 
		to each Critical Decision request. Tailoring does not imply the omission of 
		essential elements in the acquisition process that are necessary for all 
		projects, or other processes that are appropriate to a specific project’s 
		requirements or conditions. Moreover, concerning matters relating to 
		integrating safety into the early design of a facility, it is not anticipated that 
		tailoring or modification of the acquisition process would be desirable. 
		Details concerning the application of tailoring are provided in DOE M 
		413.3-1.
		
	g.	Application of Critical Decisions to Unique Projects. 

		Although most DOE projects will follow the outlined Critical Decision 
		process, there are some unique project situations where customizing the 
		process is beneficial, such as the following:
		
		(1)	Environmental Management Cleanup Projects. 

			These projects include Environmental Clean-up work, Environmental 
			Management Clean-Up Projects, and Environmental Restoration 
			projects. These “projects” could include hundreds of release sites at 
			the lowest level, that are aggregated into Environmental Protection 
			Agency regulated Operable Units or Performance Baseline Summaries. 
			These are further aggregated into a total site-wide program. 
			Decontamination and decommissioning activities may also be 
			aggregated in the same manner. Other projects may range from a 
			single project for a closure site, to disposition of a waste stream, to a 
			grouping of similar work activities or geographic locations within a 
			large site. See DOE M 413.3-1 for additional Environmental 
			Management Clean-Up Project guidance.

		(2)	Information Technology Projects. 

			Departmental Information Technology capital assets will be defined by 
			the Deputy Secretary and are characterized by: 1) their widespread and 
			continuous use among multiple Departmental organizational units; 2) 
			their vital importance to accomplishing the Department’s business 
			functions; and 3) their special importance to Agency senior 
			management. Information Technology projects are not meant to 
			encompass process or control systems that are an integral part to a 
			broader project. Additionally, this policy is applicable to 
			commercial-off-the-shelf acquisitions.

			The DOE Critical Decision process is normally tailored for 
			Information Technology projects to provide sufficient flexibility 
			during the phased or spiral approach required for these projects. 
			Generally, system design and development using a combined CD-2/3 
			process is required to support various procurement alternatives and 
			software/firmware implementation in lieu of conventional 
			construction. This tailored approach does not reduce or eliminate 
			management, performance to baselines or technical requirements. The 
			Federal Project Director uses this framework to guide development of 
			documentation to plan, manage, and execute the project and designate 
			appropriate design approvals at the Integrated Project Team level. 
	
		(3)	Design-Build Projects. 

			Design-Build is a project delivery method where a single contract is 
			awarded for both design and construction. Design-Build can be used 
			most successfully with projects that have well-defined requirements, 
			are not complex, and have limited risks. This applies to projects that 
			have few “unknowns” or new technology requirements, little to no 
			program or system integration, and are not unique or first-of-a-kind. 
			Projects such as road building, administrative facilities, fire stations, 
			and/or replication of previously accomplished projects are generally 
			the most appropriate for design-build consideration. The Design-Build 
			approach requires the development of a functional design and clearly 
			stated operating requirements that provide sufficient information to 
			allow prospective contractors to prepare bids or proposals, but also 
			allows them the flexibility to implement innovative design and 
			construction approaches, value engineering, and other cost and time 
			savings initiatives. This overall objective of the Design-Build 
			approach is to reduce the total cost to the government and deliver 
			projects more quickly than the traditional Design-Bid-Build approach.
		
			Projects for which Design-Build is an appropriate delivery method will 
			generally have clear and well-defined requirements early in the 
			process. Accordingly, at the time of CD-0, much of the cost and 
			schedule information is known along with key design criteria. For such 
			projects, CD-0 and CD-1 may be accomplished simultaneously. 
			Essentially, in requesting a simultaneous approval CD-0 and CD-1, the 
			Integrated Project Team is asserting that:

			•	There is no advantage to the government of further evaluation 
				of alternatives;

			•	The project functions and requirements are well known; and

			•	A reasonable cost and schedule range can be established.

			In some instances, design-build projects may be managed in a 
			close-coupled or fast-track fashion, whereby the initiation of facility 
			construction precedes the development of detailed facility design, e.g., 
			construction begins during the preliminary design stage of a project. In 
			these cases, the project's technical risks are typically much more 
			significant than for a traditional design and construction approach. To 
			address potential complications, aggressive risk mitigation strategies are 
			required to address the unique characteristics of close-coupled or 
			fast-track design-build projects. Risk management strategies must be 
			outlined in the risk management plan and at a minimum address: (1) all 
			technical uncertainties, (2) the establishment of design margins to 
			address the unique nature of the design, and (3) increased technical 
			oversight requirements.

			Approval of CD-0 and CD-1 establishes Design-Build as the project 
			delivery method and allows the project to go forward with development 
			of sufficient design work to establish the Performance Baseline and 
			solicitation package. Because of the maturity of the requirements, the 
			lack of complexity, and the cost and schedule knowledge gained from 
			similar efforts, establishing the Performance Baseline may be expedited. 
			In most cases, CD-3 may be requested simultaneously with CD-2. A 
			tailored External Independent Review would be accomplished to support 
			validation of the Performance Baseline.

			Design-Build projects generally will not use Project Engineering and 
			Design funds. The Project Data Sheet must be submitted for the budget 
			year in which the Design-Build contract is to be awarded and must 
			include the costs of design as part of the Total Project Cost. The program 
			office may budget for Project Engineering and Design funds if there is a 
			need to develop significant performance or technical specifications for 
			the project.
		
		(4)	Projects Requiring Long-lead Procurement. 

			For particular projects, including those requiring long-lead procurement 
			or major equipment items, it may be necessary to split CD-2 and/or -3. 
			For example, long-lead procurement might constrain construction, and an 
			early or phased CD-3 could be initiated and justified. While there is 
			potential risk in procuring equipment before the design is complete, the 
			potential schedule improvement may be significant and more than 
			compensate for the risk. The need to phase or segment CD-3 should not 
			be confused with minor, early activities that are necessary and generally 
			performed prior to CD-3. Activities such as site characterization, limited 
			access, safety, and security issues (i.e., fences, etc.) are often necessary 
			prior to CD-3, and may be pursued as long as funding approvals are in 
			place. If an early or phased CD-3 is anticipated, the need for this decision 
			and the process is normally documented in the Project Execution 
			Plan/Tailoring Strategy.

		(5)	Projects Authorized by the Annual National Defense Authorization Acts.

			The following are requirements from Title 50 United States Code for 
			projects authorized by the annual National Defense Authorization Acts:
			
			(a)	The Secretary shall submit a request for funds for a conceptual 
				design for a project if the estimated cost of the conceptual design 
				exceeds $3 million. 
				
			(b)	The conceptual design for a project shall be completed before 
				requesting funds for a construction project. 

			(c)	If the Total Estimated Cost for construction design for a project 
				exceeds $600,000, funds for that design must be specifically 
				authorized by law. 

			(d)	Construction on a project may not be started if the current Total 
				Estimated Cost of the project exceeds by more that 25% the 
				amount shown in the most recent data sheet submitted to 
				Congress.

			This is only a sampling of the more common unique projects that may require 
			tailoring of the Critical Decision process or project phases. Therefore, rather 
			than accommodate these as exceptions, guidance is provided in 
			DOE M 413.3-1.

	h.	Reviews. 

		Reviews are an important project activity and must be planned as an integral part 
		of the project and tailored appropriate to project risk, complexity, duration, and 
		Critical Decision or phase. The following is a summary of key reviews organized 
		by Critical Decision.

		(1)	CD-0. 

			(a)	Mission Validation Independent Project Review. 

				A Mission Validation Independent Project Review is a limited 
				review prior to CD-0 for Major System projects. It validates the 
				mission need and the cost range. A Value Study may also be 
				conducted, as appropriate, to assist in CD-0.

			(b)	Mission Need Statement Review. 

				The Office of Program Analysis and Evaluation within the 
				Office of the Chief Financial Officer will review the Mission 
				Need Statement and provide a recommendation to the 
				Program Secretarial Officer for projects with a Total Project 
				Cost or Environmental Management Total Project Cost 
				greater than or equal to $100M.

		(2)	CD-1. 

			(a)	Acquisition Strategy Review. Acquisition Strategies for Major 
				System Projects must be sent to the Energy Systems Acquisition 
				Advisory Board Secretariat for review by the Office of 
				Engineering and Construction Management prior to scheduling 
				CD-1 decisional briefings. The Federal Program Manager, Federal 
				Project Director and Contracting Officer must concur with the 
				Acquisition Strategy prior to the Office of Engineering and 
				Construction Management review. The Office of Engineering and 
				Construction Management will provide a recommendation to the 
				appropriate Program Secretarial Officer or Deputy/Associate 
				Administrator who holds approval authority. Approval of the 
				Acquisition Strategy does not constitute approval required by the 
				Offices of Procurement and Assistance Management (DOE or 
				National Nuclear Security Administration, as applicable) for 
				specific contract clearance purposes, including contract 
				acquisition plans. 

			(b)	Technical Independent Project Review. Prior to CD-1 approval, 
				the Program Secretarial Officer will perform a Technical 
				Independent Project Review to ensure safety and security is 
				effectively integrated into design and construction for high risk, 
				high hazard, and Hazard Category 1, 2, and 3 nuclear facilities. 
				The review should ensure safety documentation is complete, 
				accurate, and reliable for entry into the next phase of the project.
	
			(c)	Design Reviews. Design Reviews are an integral part of a project. 
				Beginning at CD-1 and continuing through the life of the project, 
				as appropriate, Design Reviews are performed by individuals 
				external to the project. Design Reviews are performed to 
				determine if a product (drawings, analysis, or specifications) is 
				correct and will perform its intended functions and meet 
				requirements. Design Reviews must be conducted for all projects 
				and must involve a formalized, structured approach to ensure the 
				reviews are comprehensive, objective, and documented.
	
		(3)	CD-2. 

			Performance Baseline Validation Review. A Performance 
			Baseline Validation Review is required to provide reasonable 
			assurance that the project can be successfully executed. 
			Independent Project Reviews are required to validate the 
			Performance Baseline for projects with a Total Project Cost or 
			Environmental Management Total Project Cost less than $100M. 
			The Acquisition Executive may request an External Independent 
			Review in lieu of an Independent Project Review through the 
			Office of Engineering and Construction Management, and must 
			do so if the Acquisition Executive has no Project Management 
			Support Office to perform the review. For all projects with a Total 
			Project Cost or Environmental Management Total Project Cost 
			greater than or equal to $100M, the Office of Engineering and 
			Construction Management utilizes the external independent 
			review in support of the performance baseline validation. As part 
			of the External Independent Review, either an Independent Cost 
			Estimate or Independent Cost Review is employed. 

		(4)	CD-3. 

			Construction or Execution Readiness Review. An External 
			Independent Readiness Review must be performed by the Office 
			of Engineering and Construction Management on Major System 
			Projects to verify execution readiness. At a minimum, this review 
			verifies the readiness of the project to proceed into construction 
			or remedial action. The findings of the Execution Readiness 
			Review and any corrective actions must be presented to the 
			Secretarial Acquisition Executive as a part of CD-3 approval. A 
			similar Independent Project Review may be performed by the 
			appropriate Program Secretarial Officer for Non-Major System 
			Projects as requested by the Acquisition Executive.

		(5)	CD-4. 

			Operational Readiness Review or Readiness Assessment. As 
			appropriate, an Operational Readiness Review or Readiness 
			Assessment is conducted prior to approving CD-4. 

i.	Baseline Management. 

		(1)	Performance Baseline Deviation. 

			A Performance Baseline deviation occurs when the approved cost, 
			schedule, performance, or scope parameters cannot be met. The Federal 
			Project Director must ensure management is promptly notified whenever 
			the project performance indicates the likelihood of a Performance 
			Baseline deviation. When a deviation occurs, the approving authority 
			must make a specific determination whether to terminate the project or 
			establish a new Performance Baseline. The Secretarial Acquisition 
			Executive must approve Performance Baseline changes under any of the 
			following circumstances for Projects: 

			•	An increase in excess of the lesser of $25M or 25% (cumulative) 
				of the original CD-2 cost baseline.

			•	A delay of six-months or greater (cumulative) from the original 
				project completion date.

			•	A change in scope that affects the ability to satisfy the mission 
				need, an inability to meet a Key Performance Parameter, or 
				non-conformance with the current approved Project Execution 
				Plan, which must be reflected in the Project Data Sheet.

			The Secretarial Acquisition Executive must approve Performance 
			Baseline changes under any of the following circumstances for 
			Clean-Up Projects: 
		
			•	An increase in excess of the lesser of $100M or 25% (cumulative) 
				of the original CD-2 Environmental Management Total Project 
				Cost baseline.

			•	A delay of one year or greater (cumulative) from the original 
				project completion date.

			•	Any change in scope that affects the site end-state.

			The Under Secretaries for Projects and the Program Secretarial Officer 
			for Environmental Management Clean-Up Projects are the approval 
			authorities for Performance Baseline changes below Secretarial 
			Acquisition Executive approval level. These approval authorities may 
			be delegated to the Program Secretarial Officers or below. New 
			Performance Baseline approval thresholds and authorities should be 
			documented in the Project Execution Plan for project changes below the 
			thresholds identified above. Additionally, all Performance Baseline 
			deviation decisions must be reported to the Secretarial Acquisition 
			Executive. These approval levels must be incorporated into the change 
			control process for each project. New performance baselines to be 
			established because of a deviation must be validated by the Office of 
			Engineering and Construction Management for projects with a Total 
			Project Cost or Environmental Management Total Project Cost greater 
			than or equal to $100M and by the Project Management Support Office 
			for projects with a Total Project Cost or Environmental Management 
			Total Project Cost less than $100M. 

		(2)	Directed Changes. 

			Project changes caused by DOE Policy Directive, Regulatory, or 
			Statutory action, such as changes in approved budget or the addition of 
			new requirements are to be called Directed Changes. Directed changes 
			follow the appropriate baseline management process.

		(3)	Change Control. 

			Change control ensures that project changes are identified, evaluated, 
			coordinated, controlled, reviewed, approved/disapproved, and 
			documented in a manner that best serves the project. The change control 
			process is defined in the Project Execution Plan. One key goal of change 
			control is to ensure Performance Baseline thresholds are not exceeded. 
			Changes can be classified into two broad categories: those that impact 
			the Performance Baseline and those that do not. Approval authority for 
			changes depends upon the impact of the change and can range from the 
			contractor to the Secretarial Acquisition Executive, usually with the 
			involvement and support of a Change Control Board. Significant changes 
			could require Congressional notification. Additional information 
			concerning change control is provided in DOE M 413.3-1.

	j.	Project Reporting and Progress Reviews. 

		Monthly project status must be reported using the web-based Project 
		Assessment and Reporting System. Approval of CD-0 initiates a requirement 
		for project status reporting which continues through the approval of CD-4 for 
		all projects with a Total Project Cost or Environmental Management Total 
		Project Cost greater than or equal to $5M. Additionally, the Acquisition 
		Executive or designee must begin holding quarterly progress reviews. The 
		requirement for quarterly reviews cannot be delegated below the Acquisition 
		Executive for Non-Major System Projects. The Secretarial Acquisition 
		Executive may delegate quarterly reviews for Major System Projects to the 
		Under Secretaries. For Environmental Management Clean-Up Projects, 
		quarterly reviews may be delegated to the Program Secretarial Officer. The 
		Office of Engineering and Construction Management must be invited to 
		quarterly reviews for all projects with a Total Project Cost greater than or 
		equal to $100M.

		At CD-2 and continuing through CD-4, critical performance information 
		must be reported in the Project Assessment and Reporting System. Projects 
		having a Total Project Cost or Environmental Management Total Project 
		Cost greater than or equal to $20M must report Earned Value performance. 
		All projects with a Total Project Cost or Environmental Management Total 
		Project Cost greater than or equal to $5M require, at a minimum, the input of 
		Key Performance Parameters, key milestones and a project performance 
		assessment (Green, Yellow, or Red) as determined by the:

			•	Federal Project Director for projects having a Total Project Cost 
				greater than or equal to $5M and less than $20M (or up to $100M for 
				Environmental Management Clean-Up projects);

			•	Program Secretarial Officer for Projects having a Total Project Cost 
				greater than or equal to $20M and less than $100M (see above bullet 
				for Environmental Management Clean-Up projects);

			•	Program Secretarial Officer for Environmental Management 
				Clean-Up Projects having a Total Project Cost greater than $100M 
				and less than or equal to $400M; and
	
			•	The Office of Engineering and Construction Management for Projects 
				having a Total Project Cost greater than or equal to $100M and 
				Environmental Management Clean-Up Projects having an Total 
				Project Cost greater than $400M. 

			Project performance assessment is determined using the following criteria:
	
			•	Green – Project is expected to meet its cost, schedule, and 
				Performance Baseline.

			•	Yellow – Project is at risk of breaching its cost, schedule, and 
				Performance Baseline.

			•	Red – Project is expected to breach its cost, schedule, and 
				Performance Baseline.

	k.	Topical Areas.

		(1)	Acquisition Strategy. 

			An acquisition strategy is a high-level description of a business and 
			technical management approach designed to achieve project 
			objectives within specified resource constraints. The acquisition 
			strategy conveys the Integrated Project Team’s approach for the 
			successful acquisition of the project, its intended outcomes, and 
			rationale for that approach. This document is a CD-1 requirement and 
			is the framework for planning, organizing, staffing, controlling, and 
			leading a project. Key elements of an Acquisition Strategy are 
			provided in DOE M 413.3-1.

		(2)	Conceptual Design/Conceptual Design Report.

			Following approval of CD-0, Approval of Mission Need, the project 
			team will commence development of the alternative strategies that will 
			satisfy the Mission Requirements identified in the Program 
			Requirements Document. These alternative strategies will culminate in 
			the proposed path forward for the project, the Conceptual Design. The 
			activities that support the development of the Conceptual Design are 
			funded through the Program Office and these costs will eventually be 
			collected and included in the project’s Total Project Cost. Title 50 U.S. 
			Code for Projects authorized by annual National Defense Authorization 
			Acts requires that any time during the development of the Conceptual 
			Design or the Conceptual Design Report the cost will exceed the $3M 
			notification threshold, Congress must be officially notified. Until the 
			approval of CD-1, Approval of Preliminary Baseline Range, there is no 
			capital funding authorized for the project, i.e., all funds expended will 
			be Program funds. In view of the Congressional notification 
			requirement, the project must keep track of the costs that are allowed 
			for the Conceptual Design.

			The specific information that is included in the Conceptual Design and 
			the allowable and prohibited costs are identified in DOE M 413.3. As a 
			minimum, the Conceptual Design should develop the following: the 
			scope required to satisfy the Program Mission requirements, the project 
			feasibility and attainment of specified performance levels, reliable cost 
			and schedule range estimates, project criteria and design parameters, 
			and identification of requirements and features. 

		(3)	Earned Value Management System. 

			An Earned Value Management System is the integrated set of policies, 
			processes, procedures, systems, and practices that meet the intent of the 
			guidelines identified in ANSI/EIA-748-A-1998. This system is generally 
			documented by a system description and procedures that translate the 
			Earned Value Management Policy into specific organizational 
			approaches of how the 32 guidelines in ANSI/EIA-748-A-1998 will be 
			executed. For projects executed under firm fixed price contracts or level 
			of effort contracts, the Secretarial Acquisition Executive/Acquisition 
			Executive may approve an alternative performance management 
			system. The Earned Value Management System or alternative 
			performance management system is described in the Project Execution 
			Plan. A complete description of the Earned Value Management System 
			capabilities are provided in ANSI/EIA-748-A-1998 and is discussed in 
			the DOE M 413.3-1.

		(4)	Environment, Safety and Health Documentation Development. 

			At CD-1, for Hazard Category 1, 2, and 3 nuclear projects, a Conceptual 
			Safety Design Report is developed to:

			(a)	Document and establish a preliminary inventory of hazardous 
				materials, including radioactive materials and chemicals; 
		
			(b)	Document and establish the preliminary hazard categorization of 
				the facility; 
		
			(c)	Identify and analyze primary facility hazards and facility Design 
				Basis Accidents; 

			(d)	Provide an initial determination, based on preliminary hazard 
				analysis, of Safety Class and Safety Significant Structures, 
				Systems, and Components; 

			(e)	Include a preliminary assessment of the appropriate Seismic 
				Design Category for the facility itself as well as Safety 
				Significant Structures, Systems, and Components; 

			(f)	Evaluate the security hazards that can impact the facility safety 
				basis (if applicable); and 

			(g)	Include a commitment to the nuclear safety design criteria of 
				DOE O 420.1 (or proposed alternative criteria). 

			At CD-2, a Preliminary Safety Design Report is developed from the 
			Conceptual Safety Design Report to reflect more refined analyses based 
			on the evolving design and safety integration activities during 
			preliminary design. The Preliminary Safety Design Report should 
			include the results of process hazards analyses and confirm or adjust, as 
			appropriate, the items included in the Conceptual Safety Design Report. 
			At CD-3, a Preliminary Documented Safety Analysis Report is prepared 
			and updates the safety information in the Preliminary Safety Design 
			Report and identifies and justifies changes from the design approach 
			described in the Preliminary Safety Design Report. At CD-4, a 
			Documented Safety Analysis Report is developed based on information 
			from the Preliminary Documented Safety Analysis Report and the 
			Safety Evaluation Report. Technical Safety Requirements are developed 
			to document and establish specific parameters and requisite actions for 
			safe facility operation. DOE-STD-1189, as amended, provides the 
			technical guidance on the preparation of nuclear facility safety 
			documents.

			For CD-1, projects involving facilities that are below Hazard Category 3 
			threshold as defined in 10 CFR 830, Subpart B, must prepare a 
			Preliminary Hazard Analysis Report to identify and evaluate all 
			potential hazards and establish a preliminary set of safety controls. 
			Hazardous chemicals are analyzed in accordance with Integrated Safety 
			Management requirements (DOE P 450.4), 29 CFR 1910.119, Process 
			Safety Management of Highly Hazardous Chemicals, and 40 CFR 68, 
			Chemical Accident Prevention Provisions. For CD-2, a Hazard Analysis 
			Report is developed by updating the Preliminary Hazard Analysis 
			Report to include any new or revised information on facility hazards 
			and safety design. For CD-3 and -4, hazard analysis and controls are 
			updated in the Hazard Analysis Report 

			All projects must comply with environmental protection requirements 
			including National Environmental Policy Act documentation, 
			anticipated permitting requirements, and cost-effective environmental 
			stewardship-high performance sustainable building principles. A 
			Construction Project Safety and Health Plan is prepared prior to 
			construction activities per 10 CFR 851 Appendix A. paragraph 1(d). An 
			Operational Readiness Review or Readiness Assessment is conducted 
			for Hazard Category 1, 2, and 3 nuclear projects in accordance to DOE 
			O 425.1C. The Program Secretarial Officer will need to determine what 
			level of readiness review is needed for projects involving facilities that 
			are below Hazard Category 3 threshold.

		(5)	Integrated Project Team. 

			The Integrated Project Team, organized and led by the Federal Project 
			Director, is an essential element in DOE’s acquisition process and is 
			used during all phases of a project’s life cycle. This team consists of 
			professionals representing diverse disciplines with the specific 
			knowledge, skills, and abilities to support the Federal Project Director 
			in successfully executing a project. The team membership will change 
			as a project progresses from initiation to closeout to ensure the 
			necessary skills are always represented to meet project needs. Team 
			membership may be full or part time, depending upon the scope and 
			complexity of a project. The Federal Project Director and the team will 
			prepare and maintain a Team Charter that describes: 

			(a)	membership; 
	
			(b)	responsibilities and authority; 

			(c)	leads (as appropriate); 

			(d)	meetings; 

			(e)	reporting; and 

			(f)	operating guidance. 

			Additional information on Integrated Project Teams is provided in DOE 
			M 413.3-1.

		(6)	Integrated Safety Management System. 
	
			The Department is committed to performing all work so missions can 
			be accomplished with adequate controls in place to protect the public, 
			workers, and the environment. The fundamental premise of Integrated 
			Safety Management System is that accidents are preventable through 
			early and close attention to planning, design, and physical execution of 
			a project. The Integrated Safety Management System is designed to 
			ensure that safety is appropriately addressed throughout the life cycle of 
			a project. Identification of potential hazards must begin early in project 
			planning and continue throughout the life cycle of the project. DOE 
			policy requires safety management systems be used to systematically 
			integrate safety into management and work processes at all levels. The 
			Integrated Safety Management System is characterized by DOE’s 
			expectation that project management will effectively implement seven 
			guiding principles: 

			(a)	Line management responsibility for safety; 
	
			(b)	Clear roles and responsibilities; 
	
			(c)	Competence commensurate with responsibility; 

			(d)	Balanced priorities; 

			(e)	The Conceptual Safety Design Report must identify safety 
				standards and requirements to include preliminary seismic design 
				category for the facility itself as well as Safety Class and Safety 
				Significant Structures, Systems, and Components;

			(f)	Engineered controls tailored to the functions being designed or 
				performed; and

			(g)	Approval to proceed. 

			Tailoring is to be applied to a project’s Integrated Safety 
			Management System to enable tasks to be managed at the 
			appropriate levels. In effect, management systems function to 
			optimize task planning and performance to enable those closest 
			to the task plan to assume responsibility. Additional Integrated 
			Safety Management System information is provided in DOE M 
			413.3-1 and the OECM, Project Management Practices, 
			Integrated Safety, Revision E, June 2003. This document defines 
			the five Integrated Safety Management core functions:
	
			(h)	Define work scope;

			(i)	Analyze hazards;

			(j)	Establish and implement controls;

			(k)	Perform work/design; and 
	
			(l)	Provide feedback and improvement.

		(7)	Key Performance Parameters. 
		
			A Key Performance Parameter is a vital characteristic of the project or 
			facility mission. It is a characteristic, function, requirement, or design 
			basis that if changed would have a major impact on the system or 
			facility performance, schedule, cost, and/or risk; or, the ability of an 
			interfacing project to meet its mission requirements. They could be 
			applicable either to the overall system/facility level as a whole and/or to 
			one or more major subsystems. Parameters that are appropriate for Key 
			Performance Parameters are those that express performance in terms of 
			accuracy, capacity, throughput, quantity, processing rates, purity, or 
			others that define how well a system, facility, or other type of project 
			will perform. Additional details concerning the application of Key 
			Performance Parameters are provided in DOE M 413.3-1.

		(8)	Performance Baseline. 

			The Performance Baseline, as established in the Project Execution Plan, 
			defines the cost, schedule, performance, and scope commitment to 
			which the Department must execute a project. When the development 
			effort has reached a phase where the requirements and design are 
			mature and the uncertainty and risks have been eliminated, reduced, 
			mitigated, or accepted a project is able to establish the parameters 
			within which it will be executed. These key parameters, when 
			completely identified, define the Performance Baseline. The 
			Performance Baseline includes the entire project budget (total cost of 
			the project including contingency) and represents DOE’s commitment 
			to the Congress and the Office of Management and Budget. The 
			Performance Baseline must be controlled, tracked, and reported from 
			the beginning to the end of a project to ensure consistency between the 
			Project Execution Plan, the Project Data Sheet, and the Exhibit 300 (a 
			requirement of Office of Management and Budget Circular A-11, Part 
			7). 

		(9)	Project Execution Plan. 

			The Project Execution Plan is the core document for management of a 
			project. The Federal Project Director is responsible for the preparation 
			of this document. It establishes the policies and procedures to be 
			followed to manage and control project planning, initiation, definition, 
			execution, and transition/closeout, and uses the outcomes and outputs 
			from all project planning processes, integrating them into a formally 
			approved document. A Project Execution Plan includes an accurate 
			reflection of how the project is to be accomplished, resource 
			requirements, technical considerations, risk management, configuration 
			management, and roles and responsibilities. A preliminary Project 
			Execution Plan is required to support CD-1. This document continues to 
			be refined throughout a project’s life cycle and revisions are 
			documented through the configuration management process. Key 
			elements of a Project Execution Plan are provided in DOE M 413.3-1. 

		(10)	Quality Assurance. 

			Quality Assurance begins at project inception and continues through the 
			project’s life cycle. The Federal Project Director is responsible for 
			planning and implementing a Quality Assurance Program for the project. 
			Quality affects cost, availability, effectiveness, safety, and performance. 
			Appropriate aspects of Quality Assurance need to be considered during 
			the preparation of project documents. The project’s application of 
			Quality Assurance is documented in either the organizational or 
			project-specific Quality Assurance Program that addresses 10 basic 
			criteria: program, personnel training and qualification, quality 
			improvement, documents and records, work processes, design, 
			procurement, inspection and acceptance, management access, and 
			independent assessment. The key requirements/elements of a Quality 
			Assurance Program are provided in DOE O 414.1C and 10 CFR 830 
			Subpart A.

		(11)	Risk Management. 

			Risk Management is an essential element of every project. The DOE risk 
			management approach must be analytical, forward looking, structured, 
			informative, and continuous. Risk assessments are started as early in the 
			project life cycle as possible and should identify critical technical, 
			performance, schedule, and cost risks. Once risks are identified, sound 
			risk mitigation strategies and actions are developed and documented. As 
			a project progresses, new information improves additional insight into 
			risk areas and allows the continuous refinement of the risk mitigation 
			strategies. A close relationship between the Integrated Project Team and 
			the contractor promotes better understanding of program risks and assists 
			in developing and handling project risks. Additional risk management 
			information is provided in DOE M 413.3-1.
		
		(12)	Safeguards and Security. 

			Safeguards and security refers to an integrated system of activities, 
			systems, programs, facilities, and policies for the protection of classified 
			information and/or classified matter, unclassified control information, 
			nuclear materials, nuclear weapons, nuclear weapon components, and/or 
			the Department’s and its contractors’ facilities, property, and equipment. 

			In order to support overall project planning and design, applicable 
			safeguards and security requirements must be identified at the earliest 
			possible project phase. Project success will depend upon the satisfaction 
			of safeguards and security requirements. Using the preliminary 
			safeguards and security plans developed in the previous phase and the 
			increasing maturity of program planning will allow project personnel to 
			determine that all safeguards and security requirements can be met and 
			are appropriately factored into project cost and schedule.

			Following the identification of applicable safeguards and security 
			requirements, their potential impact on mission objectives; satisfaction 
			of environment, safety, and health requirements; and other aspects of the 
			project must be evaluated. Preliminary identification of alternatives 
			(including facility design and the incorporation of safeguards and 
			security technologies) must be made and these alternatives evaluated 
			with respect to their impact on mission needs, satisfaction of other 
			requirements (such as safety requirements), and other cost effectiveness. 
			The applicable safeguards and security requirements, the alternatives 
			considered in the first project phase, and the preliminary approach to 
			satisfying safeguards and security requirements must be documents and 
			this documentation should be reviewed as part of CD-0. This input 
			becomes part of the conceptual design requirements for further 
			development.
		
			Identification of potential security risks must begin early in project 
			planning as part of implementing Integrated Safeguards and Security 
			Management. DOE P 470.1 requires safeguards and security management 
			systems be used to systematically integrate security into management 
			and work practices at all levels. Approval authorities of the safeguards 
			and security documents are prepared according to DOE M 470.4-1. 
			Starting with CD-1 and continuing through CD-3, for safeguards 
			Category I, II, and III, nuclear material assets are identified and 
			vulnerability and risk assessments are performed. The Security 
			Vulnerability Assessment Report, developed in CD-1 and updated in 
			subsequent CDs, describes the methodologies used in vulnerability 
			analyses, sets forth supporting information used, provides the results of 
			vulnerability analyses and risk assessments, and establishes risk ratings. 
			A security plan is developed and submitted to DOE for approval.

			Identification of potential sources of elevated safeguards and security 
			risk and/or avoidable safeguards and security costs must begin early in 
			project planning and continue as project planning and design efforts 
			proceed. DOE P 470.1 requires that a balance must be achieved among 
			safeguards and security, programmatic, and operational considerations 
			and that safeguards and security strategy must be tailored to the work 
			being performed to mitigate risk. Achievement of this balance and the 
			tailoring of safeguards and security strategy within capital projects is 
			best accomplished through the systematic application of security 
			expertise operating in conjunction with the project management system. 
			To that end, the preliminary assessment of potential safeguards and 
			security concerns and alternatives developed prior to CD-0 must continue 
			and the results be documented as the project matures. A critical review of 
			the integration of safeguards and security into the overall project plan 
			and design must be included as a portion of the CD-1 decision process. 

			Prior to CD-2, the set of applicable safeguards and security requirements, 
			the methods selected to satisfy those requirements, and any potential risk 
			acceptance issues must be reviewed and validated as complete and 
			accurate. During the CD-2 decision process, the Project Execution Plan 
			and the Performance Baseline must be reviewed to ensure that cost, 
			schedule, and integration aspects of safeguards and security are 
			appropriately addressed, that all feasible risk mitigation has been 
			identified, and that the safeguards and security concerns for which 
			explicit line management risk acceptance will be required are 
			appropriately supported. 

6.	KEY ROLES AND RESPONSIBILITIES. 

	Three themes regarding roles and responsibilities necessary to achieve defined project 
	objectives as well as the objectives of this Order include:
	
	•	Strengthening line management accountability for successful project 
		management results;

	•	Clearly defining the roles, responsibilities, authority, and accountability of the 
		Federal Project Management Team relative to the contractor Project 
		Management Team; and

	•	Developing effective Integrated Project Teams to assist the Federal Project 
		Director in planning, programming, budgeting, and successfully acquiring 
		capital assets.

	Line managers are responsible for successfully developing, executing, and managing 
	projects within the approved Performance Baseline. Delegation of authority from one 
	line manager to a lower-level line manager must be documented and consistent with 
	DOE delegation authorities and the qualifications of the lower-level line manager. 
	Although the authority and responsibility for decision-making may be delegated to a 
	lower-level manager, the senior manager remains accountable for the decisions made by 
	subordinate managers. Key roles and responsibilities of line managers are described in 
	the following sections:

	a.	Deputy Secretary.

		(1)	Serves as the senior manager responsible and accountable for all project 
			acquisitions.

		(2)	Exercises decision-making authority, including Critical Decisions for all 
			Major System Projects.

		(3)	Identifies special interest projects and ensures senior executive-level 
			quarterly reviews are provided for those projects.

		(4)	Approves disposition of projects and Performance Baseline changes at 
			the Secretarial Acquisition Executive approval level upon Performance 
			Baseline deviations.

		(5)	Serves as Chair for the Energy Systems Acquisition Advisory Board.

		(6)	Approves site selection for facilities at new sites.

		(7)	Conducts quarterly project performance reviews for Major System 
			Projects, which may be delegated to the Under Secretaries.

	b.	Under Secretaries. 

		(1)	Receive Acquisition Executive authority from the Secretarial Acquisition 
			Executive, as appropriate.

		(2)	Delegate Acquisition Executive authority, as appropriate (refer to 
			Table 1).

		(3)	Exercise decision-making authority, including Critical Decisions, 
			functioning as the Acquisition Executive.

		(4)	Hold line accountability for applicable program and capital asset project 
			execution and implementation of policy.

		(5)	Hold accountability for project-related site environment, safety and 
			health, and safeguards and security.

		(6)	Serve as Chair and appoint members for Acquisition Advisory Boards.

		(7)	Approve disposition of projects and Performance Baseline changes below 
			Secretarial Acquisition Executive approval level upon Performance 
			Baseline deviations (may be delegated to Program Secretarial Officers).

		(8)	Maintain a list of special interest projects and ensure senior 
			executive-level quarterly reviews are provided for those projects.

		(9)	Establish Project Management Support Offices or delegate this 
			responsibility to Program Secretarial Officers.

		(10)	Address and resolve issues between projects reporting to them.

		(11)	Conduct quarterly project performance reviews when serving as the 
			Acquisition Executive. These reviews may be delegated to the Program 
			Secretarial Officer.

	c.	Program Secretarial Officers and Deputy Administrators/Associate 
		Administrators for the National Nuclear Security Administration.

		(1)	Hold line accountability for applicable program and capital asset project 
			execution and implementation of policy.

		(2)	Hold accountability for project-related site environment, safety and 
			health, and safeguards and security.

		(3)	Approve Mission Need Statement documents and Acquisition Strategy 
			documents for all capital asset projects (cannot be delegated).

		(4)	Approve disposition of projects and Performance Baseline changes below 
			Secretarial Acquisition Executive approval level following Performance 
			Baseline deviations. If delegated, this authority cannot be further 
			delegated.

		(5)	Exercise decision-making authority, including Critical Decisions when 
			functioning as Acquisition Executive.

		(6)	Approve CD-0 for all projects with a Total Project Cost or Environmental 
			Management Total Project Cost less than $100M (cannot be delegated).

		(7)	Delegate Acquisition Executive functions, as appropriate (refer to Table 
			1).

		(8)	Nominates Federal Project Directors, when the Acquisition Executive is 
			above the Program Secretarial Officer, no later than CD-1 (can be 
			delegated). The Federal Project Director appointment is subject to the 
			approval of the Acquisition Executive.

		(9)	Serve as Chair and appoint members for Acquisition Advisory Boards.

		(10)	Direct Independent Project Reviews.

		(11)	Establish Project Management Support Offices when responsibility is 
			delegated or directed by the Under Secretaries.

		(12)	Ensures that safety is fully integrated into design and construction for 
			high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear 
			facilities.

		(13)	Appoint a Safety Basis Approval Authority no later than CD-0 for 
			projects including the design and construction of Hazard Category 1, 2, 
			and 3 nuclear facilities, or for projects including major modifications 
			thereto.

	d.	Project Management Support Offices (when established).

		(1)	Provide independent oversight and report directly to the Under 
			Secretaries, or Program Secretarial Officer, as appropriate.

		(2)	Serve as the Secretariat for the Program Secretarial Officer/National 
			Nuclear Security Administration-level Advisory Board functions.

		(3)	Coordinate quarterly performance reports.

		(4)	Perform Performance Baseline Validation Independent Project Review 
			and other Independent Project Reviews as required by the Program 
			Secretarial Officer. 

		(5)	Develop Program-specific implementing guidance, policies, and 
			procedures. 

		(6)	Collect, analyze, and disseminate lessons learned and “best practices.”

		(7)	Coordinate with other DOE organizations and offices, including the 
			Office of Engineering and Construction Management, to ensure 
			effective and consistent implementation of project management 
			policies and directives.

		(8)	Provide assistance and oversight to line project management 
			organizations.

		(9)	Analyze project management execution issues.
		
		(10)	Actively assist senior management on issues related to project 
			management performance, including implementation of corrective 
			actions.

		(11)	Provide support to the Federal Project Directors. 

		(12)	Validate the Performance Baseline for capital asset projects with a 
			Total Project Cost or Environmental Management Total Project Cost 
			greater than or equal to $20M and less than $100M.

	e.	Program Managers and Heads of Field Organizations. 

		(1)	Direct initial project planning and execution roles for projects assigned 
			by the Acquisition Executive.

		(2)	Initiate definition of mission need based on input from Sites, 
			Laboratories, and Program Offices.

		(3)	Establish the Integrated Project Team.

		(4)	Oversee development of project definition, technical scope, and budget to 
			support mission need.

		(5)	Initiate development of the Acquisition Strategy before CD-1 (during the 
			period preceding designation of the Federal Project Director).

		(6)	Perform functions as Acquisition Executive when so delegated.

		(7)	Develop project performance measures, and monitor and evaluate project 
			performance throughout the project’s life cycle.

		(8)	Allocate resources throughout the program.

		(9)	Oversee the project line-management organization and ensure the line 
			project teams have the necessary experience, expertise, and training in 
			design engineering, safety and security analysis, construction, and 
			testing.

		(10)	Serve as the Federal Project Director until the Federal Project Director is 
			appointed.

		(11)	Ensures that safety is fully integrated into design and construction for 
			high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear 
			facilities.

	f.	Acquisition Executives. 

		The following roles and responsibilities are for illustrative purposes, and each 
		designated Acquisition Executive is guided by the specific limits of his/her 
		delegated authority.

		(1)	Approve Critical Decisions (CD-0 cannot be delegated below the 
			Program Secretarial Officer level).

		(2)	Appoint and Chair Acquisition Advisory Boards to provide advice and 
			recommendations on key project decisions.

		(3)	Approve the appointment of the Federal Project Director.

		(4)	Designate the Design Authority at CD-1.

		(5)	Monitor the effectiveness of Federal Project Directors and their 
			support staff.

		(6)	Approve project changes in compliance with change control levels 
			identified in Project Execution Plans.

		(7)	Conduct monthly and quarterly project performance reviews.

		(8)	Ensures that safety is fully integrated into design and construction for 
			high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear 
			facilities.

	g.	Federal Project Director. 

		Successful performance of DOE projects depends on professional and effective 
		project management by the Federal Project Director. The Federal Project 
		Director is responsible and accountable to the Acquisition Executive/Program 
		Secretarial Officer or delegated authority, as appropriate, for executing the 
		project. 

		The Federal Project Director’s assigned project must meet cost, schedule and 
		performance targets unless circumstances beyond the control of the Project 
		direct result in cost overruns and/or delays. Federal Project Directors must 
		demonstrate initiative in incorporating and managing an appropriate level of risk 
		to ensure best value for the government. In cases where significant cost overruns 
		and/or delays occur, the Federal Project Director alerts senior management in a 
		timely manner and takes appropriate steps to mitigate these cost overruns or 
		delays.

		Roles and responsibilities of the Federal Project Director’s team must be clearly 
		defined relative to the contractor management team. Further guidance is 
		provided in DOE M 413.3-1.

		(1)	Attains and maintains certification in concert with the requirements 
			outlined in DOE O 361.1A before they are delegated authority to serve as 
			a Federal Project Director.

		(2)	Plans, implements, and completes a project using a Systems Engineering 
			approach.

		(3)	Initiates development and implementation of key project 
			documentation (e.g., Project Execution Plan).

		(4)	Defines project cost, schedule, performance, and scope baselines.

		(5)	Is responsible for design, construction, environmental, safety, 
			security, health, and quality efforts performed comply with the 
			contract, public law, regulations, and Executive Orders.

		(6)	Is responsible for timely, reliable, and accurate integration of 
			contractor performance data into the project’s scheduling, 
			accounting, and performance measurement systems.

		(7)	Evaluates and verifies reported progress; makes projections of 
			progress and identifies trends.

		(8)	Serves as the single point of contact between Federal and contractor 
			staff for all matters relating to a project and its performance.

		(9)	Serves as the Contracting Officer’s Representative, as determined by 
			the Contracting Officer.

		(10)	Leads the Integrated Project Team and provides broad program 
			guidance. Delegates appropriate decision-making authority to the 
			Integrated Project Team members. 

		(11)	Prepares and maintains the Integrated Project Team Charter and 
			operating guidance with Integrated Project Team support.

		(12)	Approves changes in compliance with the approved change control 
			process documented in the Project Execution Plan.

		(13)	Ensures that safety is fully integrated into design and construction for 
			high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear 
			facilities.

	h.	Departmental Staff and Support Offices. 

		Departmental Staff and Support Offices develop policy and related 
		implementing guidance, perform review functions, and provide advice and 
		recommendations to Department leadership. Key roles and responsibilities of 
		these offices regarding the acquisition of capital assets follow.

	i.	Office of Health, Safety and Security.

		(1)	Serves as a member of the Energy Systems Acquisition Advisory 
			Board.

		(2)	Advises the Deputy Secretary in his/her role as the Secretarial 
			Acquisition Executive on environmental, safety, and security matters 
			related to all Critical Decision approvals.

		(3)	Serves on the Independent Project Review as a team member at the 
			request of the Secretarial Acquisition Executive, Program Secretarial 
			Officer, Program Manager, Operations/Field Office Manager, or 
			Federal Project Director.

		(4)	Participates on External Independent Reviews as an observer at the 
			request of the Office of Engineering and Construction Management.

		(5)	Participates in safety and security documentation and Quality 
			Assurance reviews for acquisition projects at the request of the Office 
			of Engineering and Construction Management and/or the Acquisition 
			Executive when considered appropriate.

		(6)	Participates in Operational Readiness Reviews or Readiness 
			Assessments at the request of the line organizations.

		(7)	Supports the Central Technical Authorities as requested.

	j.	Office of the Chief Information Officer.

		(1)	Holds delegated Acquisition Executive authority over Departmental 
			Information Technology Projects between $5M < $100M.

		(2)	Develops and maintains Department-wide policy, requirements, and 
			guidance for Information Technology projects, including Information 
			Technology hardware, software and application, and capital assets.

		(3)	Advises and provides programmatic support to ensure that Information 
			Technology is acquired and information resources are managed in 
			accordance with all applicable statutory, regulatory, and agency 
			requirements.

		(4)	Provides Information Technology investment management process 
			assistance to Program Offices, field elements, and contractor 
			locations, as requested.

		(5)	Regularly collects process performance measurement information, 
			and prepares a summary report on the status and performance of 
			Information Technology investments.

		(6)	Establishes Enterprise Architecture policy and practice within DOE 
			to ensure the development and maintenance of a sound and integrated 
			Information Technology portfolio of investments that are aligned to 
			the strategic business goals of the Department.
		
	k.	Office of Engineering and Construction Management within the Office of 
		Management. 

		(1)	Serves as DOE’s principal point of contact relating to project 
			management.

		(2)	Develops policy, requirements, and guidance for the acquisition of 
			capital assets.

		(3)	Assist in the planning, programming, budgeting, and execution 
			process for the acquisition of capital assets in coordination with the 
			Program Secretarial Officers and Project Management Support 
			Offices.

		(4)	Supports the Office of the Secretary, the Secretarial Acquisition 
			Executive, the Under Secretaries, and the Program Secretarial Officer 
			in the Critical Decision process; and oversight of the acquisition 
			management process.

		(5)	Serves as Secretariat for the Energy Systems Acquisition Advisory 
			Board.

		(6)	Serves as an Acquisition Advisory Board member for Non-Major 
			System Projects with a Total Project Cost or Environmental 
			Management Total Project Cost greater than or equal to $100M.

		(7)	Manages the Project Management Career Development Program.

		(8)	Manages the Earned Value Management System certification process.

		(9)	Reviews Acquisition Strategies for Major System Projects.

		(10)	Maintains a corporate project reporting capability.

		(11)	Establishes, maintains, and executes a corporate independent review 
			capability to provide an independent assessment and analysis of 
			project planning, execution, and performance.

		(12)	Validates the Performance Baseline for all capital asset projects with 
			a Total Project Cost or Environmental Management Total Project 
			Cost greater than or equal to $100M to permit inclusion in the DOE 
			annual budget.

	l.	Office of Program Analysis and Evaluation. 

		Reviews Mission Need Statements for all capital asset projects with a Total 
		Project Cost or Environmental Management Total Project Cost greater than or 
		equal to $100M, and makes a recommendation to Program Secretarial Officer 
		prior to CD-0.

	m.	Integrated Project Team. 

		(1)	Supports the Federal Project Director.

		(2)	Develops a project contracting strategy.

		(3)	Ensures project interfaces are identified, defined, and managed to 
			completion.

		(4)	Identifies, defines, and manages to completion the project environmental, 
			safety, health, security, and quality assurance requirements.

		(5)	Identifies and defines appropriate and adequate project technical scope, 
			schedule, and cost parameters.

		(6)	Performs periodic reviews and assessments of project performance and 
			status against established performance parameters, baselines, milestones, 
			and deliverables.

		(7)	Plans and participates in project reviews, audits, and appraisals as 
			necessary.

		(8)	Reviews all Critical Decision packages and recommend 
			approval/disapproval.

		(9)	Reviews and comments on project deliverables (e.g., drawings, 
			specifications, procurement, and construction packages).

		(10)	Reviews change requests (as appropriate) and support Change Control 
			Boards as requested.

		(11)	Participates, as required, in Operational Readiness Reviews or Readiness 
			Assessments.
		
		(12)	Supports preparation, review, and approval of project completion and 
			closeout documentation.

		(13)	Ensures that safety is fully integrated into design and construction for 
			high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear facilities.

	n.	Central Technical Authorities. 
		
		The Central Technical Authorities are responsible for maintaining operational 
		awareness, especially with respect to complex, high-hazard nuclear operations, 
		and ensuring the Department’s nuclear safety policies and requirements are 
		implemented adequately and properly. In this context, it is important to 
		recognize that the Central Technical Authorities have responsibilities related to 
		nuclear safety directives that apply to projects. The overall roles and 
		responsibilities of the Central Technical Authorities include:

		(1)	Concur with the determination of the applicability of DOE Directives 
			involving nuclear safety included in contracts pursuant to DEAR 48 CFR 
			970.5204-2(b).

		(2)	Concur with nuclear safety requirements included in contracts pursuant 
			to DEAR 48 CFR 970.5204-2.
		
		(3)	Concur with all exemptions to nuclear safety requirements in contracts 
			that were added to the contract pursuant to DEAR 48 CFR 970.5204-2.
	
		(4)	Recommend to the Assistant Secretary for Environment, Safety and 
			Health issues and proposed resolutions concerning DOE safety 
			requirements, concur in the adoption or revision of nuclear safety 
			requirements (including supplemental requirements), and provide 
			expectations and guidance for implementing nuclear safety requirements 
			for use by DOE employees and contractors.

	o.	Chief of Defense Nuclear Safety and Chief of Nuclear Safety. 

		The Chiefs (and staff) are responsible for evaluating nuclear safety issues and 
		providing expert advice to the Central Technical Authorities and other senior 
		officials. For Hazard Category 1, 2, or 3 nuclear facilities, the Chief:

		(1)	Participates as part of the Energy Systems Acquisition Advisory Board, 
			or similar advisory boards.

		(2)	Provides support to both the Central Technical Authorities and 
			Acquisition Executive regarding the effectiveness of efforts to integrated 
			safety into design at each of the Critical Decisions, and as requested 
			during other project reviews.

		(3)	Validates that integration of design and safety basis activities include the 
			use of a system engineering approach tailored to the specific needs and 
			requirements of the project.

		(4)	Determines that nuclear facilities have incorporated the concept of 
			defense-in-depth into the facility design process.

		(5)	Validates that Federal personnel assigned to the Integrated Project Team 
			as nuclear safety experts are appropriately qualified.

	p.	Energy Systems Acquisition Advisory Board. 

		The Energy Systems Acquisition Advisory Board advises the Secretarial 
		Acquisition Executive on Critical Decisions related to Major System Projects, 
		site selection, and Performance Baseline deviation dispositions.

	q.	Energy Systems Acquisition Advisory Board Membership. 

		(1)	Secretarial Acquisition Executive as Chair

		(2)	Under Secretaries

		(3)	DOE General Counsel 

		(4)	Director of Management

		(5)	Chief Financial Officer

		(6)	Director of the Office of Engineering and Construction Management

		(7)	Assistant Secretary for Environmental Management

		(8)	Chief Health, Safety and Security Officer

		(9)	Deputy Administrator for Defense Programs

		(10)	Director of the Office of Science

		(11)	Assistant Secretary for Nuclear Energy

		The Deputy Secretary may designate other Program Secretarial Officers or 
		functional staff as Energy Systems Acquisition Advisory Board members 
		(temporary or permanent) as needed.

	r.	Energy Systems Acquisition Advisory Board Secretariat. 

		The Energy Systems Acquisition Advisory Board Secretariat resides in the 
		Office of Engineering and Construction Management and provides 
		administrative and analytical support and recommendations to the Energy 
		Systems Acquisition Advisory Board.

	s.	Non-Major System Project Advisory Boards. 

		The designated Acquisition Executive will appoint an Advisory Board to 
		provide advice and recommendations on actions for projects that are not 
		designated as Major Systems. The designated Acquisition Executive is the 
		Chair of the Advisory Board. The Advisory Board replicates and conducts 
		identical functions to those performed by the Energy Systems Acquisition 
		Advisory Board. Members may be selected from within the Acquisition 
		Executive’s organization. However, at least one member from an office not 
		under the Acquisition Executive will be designated as a contributing 
		representative. The Office of Engineering and Construction Management will 
		provide a member to each Advisory Board for projects with a Total Project 
		Cost or Environmental Management Total Project Cost greater than or equal to 
		$100M. The Office of 

		Engineering and Construction Management will not be a Board member for 
		projects with a Total Project Cost or Environmental Management Total Project 
		Cost less than $100M, but may be invited to attend the Advisory Board 
		meetings. The implementing documentation and composition of each Advisory 
		Board along with meeting agendas and minutes will be provided to the Office 
		of Engineering and Construction Management.

7.	REFERENCES.

	a.	10 CFR 830, Subpart A, Quality Assurance Requirements.

	b.	10 CFR 830, Subpart B, Safety Basis Requirements.

	c.	10 CFR 830.206, Preliminary Documented Safety Analysis.

	d.	10 CFR 851, Worker Safety and Health Program.

	e.	29 CFR 1910.119, Process Safety Management of Highly Hazardous Substances.
	
	f.	40 CFR 68, Chemical Accident Prevention Provisions.

	g.	ANSI-EIA-649, National Consensus Standard for Configuration Management.

	h.	ANSI-EIA-748-A-1998, Earned Value Management Systems.

	i.	DEAR 48 CFR 970.5204-2, Integration of Environmental, Safety, and Health 
		into Work Planning and Execution.

	j.	DOE O 205.1, Department of Energy Cyber Security Management Program, 
		dated 03-21-03.

	k.	DOE P 413.1, Program and Project Management Policy for the Planning, 
		Programming, Budgeting, and Acquisition of Capital Assets, dated 06-10-00.

	l.	DOE O 425.1C, Startup and Restart of Nuclear Facilities, dated 03-13-03.

	m.	DOE O 430.2A, Departmental Energy and Utilities Management, dated 
		04-15-02.

	n.	DOE O 451.1B, Chg 1, National Environmental Policy Act Compliance Program, 
		dated 09-28-01.

	o.	DOE P 470.1, Integrated Safeguards and Security Management, dated 05-08-01.
	
	p.	DOE P 450.4, Safety Management System Policy, dated 10-15-96.

	q.	DOE P 226.1, Department of Energy Oversight Policy, dated 06-10-05.

	r.	DOE O 414.1C, Quality Assurance, dated 06-17-05.

	s.	DOE O 420.1B, Facility Safety, dated 12-22-05.

	t.	DOE M 413.3-1, Program Management for the Acquisition of Capital Assets, 
		dated 03-28-03.

	u.	DOE M 470.4-1, Safeguards and Security Program Planning and Management, 
		dated 08-26-05.

	v.	DOE O 361.1A, Acquisition Career Development Program, dated 04-19-04.

	w.	DOE O 450.1, Chg 2, Environmental Protection Program, dated 12-07-05.

	x.	DOE-STD-1189, as amended.

	y.	House Report 109-86, “Energy and Water Development Appropriations Bill, 
		2006.”

	z.	OECM, Project Management Practices, Integrated Safety, Revision E, June 2003.

	aa.	OMB Circular A-11, Part 7, Planning, Budgeting, Acquisition, and Management 
		of Capital Assets, dated June 2006; and Supplement to Part 7-Capital 
		Programming Guide.

	bb.	OMB Circular A-123, Management’s Responsibility for Internal Control, dated 
		12-21-04.

	cc.	OMB Circular A-127, Financial Management Systems, dated 07-23-93.

	dd.	OMB Circular A-130, Management of Federal Information Resources, 
		Transmittal Memorandum #4, dated 11-28-00.

8.	CONTACT. Questions concerning this Order should be directed to the Office of 
	Engineering and Construction Management, 202-586-1784.

BY ORDER OF THE SECRETARY OF ENERGY:

	CLAY SELL

	Deputy Secretary



ATTACHMENT 1. DEPARTMENTAL ELEMENTS TO WHICH

DOE ORDER 413.3A IS APPLICABLE

Office of the Secretary

Departmental Representative to the Defense Nuclear Facilities Safety Board 

National Nuclear Security Administration 

Office of Chief Financial Officer 

Office of Chief Information Officer 

Office of Civilian Radioactive Waste Management 

Office of Congressional and Intergovernmental Affairs 

Office of Economic Impact and Diversity 

Office of Electricity Delivery and Energy Reliability 

Office of Energy Efficiency and Renewable Energy 

Office of Energy Information Administration

Office of Environmental Management 

Office of Fossil Energy 

Office of General Counsel 

Office of Health, Safety and Security

Office of Hearings and Appeals 

Office of Human Capital Management 

Office of Inspector General 

Office of Intelligence and Counterintelligence

Office of Legacy Management 

Office of Management 

Office of Nuclear Energy, Science, and Technology 

Office of Policy and International Affairs 

Office of Public Affairs 

Office of Science

Secretary of Energy Advisory Board

Southeastern Power Administration

Southwestern Power Administration

Western Area Power Administration


ATTACHMENT 2. CONTRACTOR REQUIREMENTS DOCUMENT 
DOE ORDER 413.3A, Program and Project Management  
for the Acquisition of Capital Assets

This Contractor Requirements Document sets forth intended requirements to be applied to 
contractors responsible for performing program and project management of Department-owned 
facilities and for other contractors as determined by the Federal Project Director and 
Contracting Officer, in conjunction with the Federally-assigned Integrated Project Team 
members. Regardless of the performer of the work, the affected contractor is responsible for 
complying with the requirements of this Contractor Requirements Document as included in the 
contract. The contractor is responsible for flowing down Contractor Requirements Document 
requirements to subcontractors at any tier to the extent necessary to ensure contractor 
compliance.

The contractor’s project management system must satisfy the following requirements:

1.	The industry standard for Performance Management Systems, described in 
	ANSI/EIA-748-A-1998, must be implemented and self-certified on all projects with a 
	Total Project Cost greater than $20M. For projects not required to utilize an Earned 
	Value Management System (e.g., firm fixed-price contract projects), an alternative 
	Performance Management System must be described in the Project Execution Plan and 
	utilized. For projects with Total Project Cost equal to or greater than $50M, the Earned 
	Value Management System must be validated by the Office of Engineering and 
	Construction Management. It is to be used for control and reporting of project 
	performance as defined in the Project Execution Plan and no later than CD-2.

2.	Cost and schedule performance, milestone status, and financial status no later than 
	CD-2 must be reported to DOE on a monthly basis using DOE-approved work 
	breakdown structure elements and data elements for all projects with a Total Project 
	Cost greater than or equal to $20M, except firm fixed-priced contracts. The report must 
	also include variance analyses and corrective action plans that integrate cost, schedule, 
	and scope if variances exceed DOE-established reporting thresholds. Analyses of cost 
	and schedule trends, financial status, and baseline change control activity, including the 
	allocation of management reserve, potential problems, and critical issues will also be 
	reported. Reporting by the contractor may be required earlier than CD-2 as specified by 
	the Contracting Officer.

3.	For project contracts to be awarded as subcontracts by the contractor, the contractor 
	must have a written Acquisition Plan that is appropriate for the requirement and dollar 
	value of each subcontract and consistent with its contract’s provisions. The Acquisition 
	Plan for a project contract to be awarded by the contractor is to be developed by a team 
	of contractor employees including, at a minimum, the prospective Project Manager and 
	Contract Negotiator. The Acquisition Plan must receive the concurrence of both the 
	Federal Project Director and the DOE Contracting Officer.

4.	Technical performance analyses and corrective action plans must be reported to DOE 
	for variances to the project baseline objectives resulting from design reviews, 
	component and system tests, and simulations.

5.	A critical path schedule and a project master schedule must be developed and 
	maintained.

6.	Cost estimating must be an integral part of cost baseline including life cycle cost 
	development and maintenance, budget request development, and estimates at 
	completion.

7.	Project technical, cost, and schedule risks must be identified, quantified, and mitigated 
	throughout the life of the project. Risks must be identified, evaluated, and mitigation 
	strategies developed and implemented.

8.	An integrated contractor technical, cost, and schedule baseline must be developed and 
	maintained using a contractor-level Change Control Board.

9.	A configuration management process must be established that controls changes to the 
	physical configuration of project facilities, structures, systems, and components in 
	compliance with ANSI/EIA-649, National Consensus Standard for Configuration 
	Management. This process must also ensure that the configuration is in agreement with 
	the performance objectives identified in the technical baseline and the approved quality 
	assurance plan.

10.	A Value Management/Engineering process must be used that identifies high-cost 
	project activities in order to realize a maximum return on investment through the use of 
	systems engineering tradeoffs and functional analyses that identify alternate means of 
	achieving the same function at a lower life cycle cost.

11.	A quality assurance program must be developed and implemented for the contract scope 
	of work when the contractor’s requirements include DOE O 414.1C, Quality Assurance 
	or 10 CFR 830 Subpart A, Quality Assurance Requirements (as applicable).
	
12.	An Integrated Safety Management system must be developed and implemented for the 
	contract scope of work when the contractor is complying with the requirements of 
	DEAR 48 CFR 970.5223-1-, Integration of Environment, Safety and Health into Work 
	Planning and Execution.

13.	Contractors performing design for projects must at a minimum conduct a Preliminary 
	and Final Design Review, in accordance with the Project Execution Plan. For nuclear 
	projects, the design review will include a focus on safety and security systems. 
	
14.	High performance sustainable building principles must be applied to the siting, design, 
	construction, and commissioning of new facilities and major renovations of existing 
	facilities.

15.	For projects including Hazard Category 1, 2, and 3 nuclear facilities or for projects 
	including major modifications thereto (as defined in 10 CFR Part 830), the requirements 
	in DOE-STD-1189, as amended, must be fully implemented. The following documents 
	must be submitted:  Safety Design Strategy (CD-1), Conceptual Safety Design Report 
	(CD-1), Preliminary Safety Design Report (CD-2), Preliminary Documented Safety 
	Analysis (CD-3), and Documented Safety Analysis with Technical Safety Requirements 
	(CD-4). For major modifications, the Conceptual Safety Design Report and the 
	Preliminary Safety Design Report may either be separate documents or be subsumed 
	within the Preliminary Documented Safety Analysis.



ATTACHMENT 3. DEFINITIONS

1.	Acquisition Executive. The individual designated by the Secretary of Energy to 
	integrate and unify the management system for a program portfolio of projects, and 
	implement prescribed policies and practices.
	
2.	Acquisition Strategy. An acquisition strategy is a high-level business and technical 
	management approach designed to achieve project objectives within specified resource 
	constraints. It is the framework for planning, organizing, staffing, controlling, and 
	leading a project. It provides a master schedule for activities essential for project 
	success, and for formulating functional strategies and plans.

3.	Capital Assets. Capital assets are land, structures, equipment, intellectual property (e.g., 
	software), and Information Technology used by the Federal government and having an 
	estimated useful life of two or more years. Capital assets include environmental 
	restoration (decontamination and decommissioning) of land to make useful leasehold 
	improvements and land rights, and assets whose ownership is shared by the Federal 
	Government with other entities. Capital assets may be acquired in different ways: 
	purchase, construction, or manufacture; a lease-purchase or other capital lease 
	(regardless of whether title has passed to the Federal Government); or exchange. This 
	Order does not apply to land, structures, equipment, intellectual property (e.g., 
	software), or Information Technology acquired by State and local governments or other 
	entities through Financial Assistance (i.e., DOE grants and cooperative agreements), or 
	to assets acquired under General Plant Projects for maintaining infrastructure at a site.

4.	Conceptual Design. The concept for meeting a mission need. The Conceptual Design 
	process requires a mission need as an input. Concepts for meeting the need are explored 
	and alternatives considered to arrive at a set of alternatives that are technically viable, 
	affordable and sustainable.

5.	Configuration Management. The technical and administrative direction and surveillance 
	actions taken to identify and document the functional and physical characteristics of a 
	configuration item; to control changes to a configuration item and its characteristics; 
	and to record and report change processing and implementation status.

6.	Contingency. Contingency is the portion of the project budget that is available for risk 
	uncertainty within the project scope, but outside the scope of the contract. Contingency 
	is budget that is not placed on the contract, and is included in the Total Project Cost.

7.	Construction Manager. The individual or firm responsible to DOE for supervision and 
	administration of a construction project to ensure the construction contractor's 
	compliance with construction project requirements. 

8.	Contractor Requirements Document. A Contractor Requirements Document is the DOE 
	document that identifies the requirements that the Prime Contractor’s project 
	management system must satisfy (Attachment 2).

9.	Critical Decision. A formal determination made by the Secretarial Acquisition 
	Executive/Acquisition Executive at a specific point in a project’s life cycle that allows 
	the project to proceed to the next phase or Critical Decision.

10.	Deviation. A deviation occurs when the current estimate of a performance, technical, 
	scope, schedule, or cost parameter is not within the threshold values of the Performance 
	Baseline for that parameter. It is handled as a deviation, not through the normal change 
	control system.

11.	Directed Change. A change imposed on a project(s) that affects the project’s baseline. 
	Example of directed changes include, but are not limited to (a) changes to approved 
	budgets, or funding, and (b) changes resulting from DOE policy directives and 
	regulatory or statutory requirements.

12.	Earned Value. Earned Value is the budgeted value of work actually accomplished in a 
	given time. Simply defined, Earned Value represents the value of work accomplished 
	during the period. 

13.	Earned Value Management. Earned Value Management is a program and project 
	management methodology of which organization, planning, progressing, tracking, 
	management control, reporting, and communication are essential elements.

14.	External Independent Review. A project review conducted by individuals outside DOE. 
	The Office of Engineering and Construction Management selects an appropriate 
	contractor to perform these reviews.

15.	Final Design. Completion of the design effort and production of all the approved design 
	documentation necessary to permit procurement, construction, testing, checkout, and 
	turnover to proceed. Final design occurs between Critical Decision-2 and -3.

16.	Independent Cost Estimate. A “bottoms-up” documented, independent cost estimate that 
	has the express purpose of serving as an analytical tool to validate, crosscheck, or 
	analyze cost estimates developed by project proponents.

17.	Independent Cost Review. An essential project management tool used to analyze and 
	validate an estimate of project costs by individuals having no direct responsibility for 
	project performance.

18.	Independent Project Review. Independent Project Reviews are important project 
	management tools and serve to verify the project’s mission, organization, development, 
	processes, technical requirements, baselines, progress, etc. Independent Project Reviews 
	are performed by reviewers from within or outside the Program, but having no 
	association with the project being reviewed. 

19.	Integrated Project Team. An Integrated Project Team is a cross-functional group of 
	individuals organized for the specific purpose of delivering a project to an external or 
	internal customer.

20.	Integrated Safety Management. The application of the integrated safety management 
	system to a project or activity. The fundamental premise of Integrated Safety 
	Management is that accidents are preventable through early and close attention to 
	safety, design, and operation, and with substantial stakeholder involvement in teams 
	that plan and execute the project, based on appropriate standards.

21.	Key Performance Parameters. A vital characteristic of a project or facility mission. A 
	characteristic, function, requirement, or design basis, that if changed, would have a 
	major impact on the facility or system performance, scope, schedule, cost and/or risk, or 
	the ability of an interfacing project to meet its mission requirements. Thus, a Key 
	Performance Parameter may be a performance, design or interface requirement. 
	Parameters that are appropriate for Key Performance Parameters are those that express 
	performance in terms of accuracy, capacity, throughput, quantity, processing rate, 
	purity, or others that define how well a system, facility or other project will perform.

22.	Life Cycle Costs. The sum total of the direct, indirect, recurring, nonrecurring, and 
	other related costs incurred or estimated to be incurred in the design, development, 
	production, operation, maintenance, support, long-term stewardship (if applicable), and 
	final disposition of a project/system over its anticipated useful life span. Where system 
	or project planning anticipates use of existing sites or facilities, restoration and 
	refurbishment costs are included in the life cycle costs.

23.	Line Item. An appropriation by Congress for a specific effort, activity, or project.

24.	Long-Lead Procurement. Equipment or material that must be procured well in advance 
	of the need for the materials because of long delivery times.

25.	Maintenance. Day-to-day work required to sustain property in a condition suitable for 
	its designated purposes, including preventive, predictive, and corrective maintenance.

26.	Major System. A project with a Total Project Cost of greater than or equal to $750M or 
	an Environmental Management Total Project Cost of $1B or designated by the Deputy 
	Secretary.

27.	Management Reserve. An amount of the total contract budget withheld for management 
	control purposes by the contractor. Management Reserve is not part of the Performance 
	Measurement Baseline.

28.	Mission Need Statement. A concise document that details a mission requirement the 
	Department cannot meet through nonmaterial method. 

29.	Non-Major System. Any project with a Total Project Cost less than $750M or an 
	Environmental Management Total Project Cost less than $1B.

30.	Performance Baseline. The collective key performance, scope, cost, and schedule 
	parameters, which are defined for all projects. Performance Baseline includes the entire 
	project budget (total cost of the project including contingency) and represents DOE’s 
	commitment to Congress.

31.	Performance Measurement Baseline. The Performance Measurement Baseline is the 
	baseline that encompasses all project work packages and planning packages. The 
	Performance Measurement Baseline provides a view from the bottom-up where work 
	packages are summed within the Work Breakdown Structure. Management Reserve, 
	contingency, profit, fee and similar cost items separately identified in the contract are 
	not part of the Performance Measurement Baseline because no work is associated with 
	those budgets.

32.	Project. A unique effort that supports a program mission having defined points for 
	starting and ending, undertaken to create a product, facility, or system and containing 
	interdependent activities planned to meet a common objective or mission. A project is a 
	basic building block (in relation to a program) that is individually planned, approved, 
	and managed. A project is not constrained to any specific element of the budget 
	structure (e.g., operating expense, plant or capital equipment). Projects include planning 
	and execution of construction, assembly, renovation, modification, environmental 
	restoration, decontamination and decommissioning, large capital equipment, and 
	technology development activities. Work that does not include the above elements, e.g., 
	basic research, grants, ordinary repairs, maintenance, and operation of facilities are not 
	considered projects. However, these activities can be managed as projects.

33.	Project Data Sheet. A generic term defining the document that contains summary 
	project data and the justification required to include the entire project effort as a part of 
	the Departmental budget.

34.	Project Engineering and Design. Design funds established for use on preliminary 
	design, which are Operating Expense funds. Typically, Project Engineering and Design 
	funds are used for preliminary and final design and related activities for 
	design-bid-build strategies, and for preliminary design and related costs in design-build 
	strategies.

35.	Risk Management. Effective risk management is an essential element of every project. 
	The DOE risk management concept is based on the principles that risk management 
	must be analytical, forward-looking, structured, informative, and continuous. Risk 
	assessments should be performed as early as possible in the project life cycle and 
	should identify critical technical, performance, schedule, and cost risks. Once risks are 
	identified, sound risk mitigation strategies and actions should be developed and 
	documented. 
	
36.	System Engineering. A proven, disciplined approach that supports management in 
	clearly defining the mission or problem; managing system functions and requirements; 
	identifying and managing risk; establishing bases for informed decision-making; and, 
	verifying products and services meet customer needs. The goal of the System 
	Engineering process is to transform mission operational requirements into system 
	architecture, performance parameters, and design details. 


37.	Total Project Cost. DOE has traditionally identified project costs in two categories: (1) 
	Total Estimated Cost, and (2) Other Project Cost. The sum of the Total Estimated Cost 
	and Other Project Costs make up the Total Project Cost. 

	•	Total Estimated Cost includes project costs incurred after CD-1 such as costs 
		associated with the acquisition of land and land rights; engineering, design, and 
		inspection; direct and indirect construction/fabrication; and the initial equipment 
		necessary to place the plant or installation in operation. Total Estimated Cost may 
		be funded as an operating or capital expense. 

	•	Other Project Costs include all project costs that are not identified as Total 
		Estimated Cost costs. Generally, Other Project Costs are costs incurred during the 
		Initiation and Definition Phases for planning, conceptual design, research and 
		development, and during the Execution Phase for startup and operation. Other 
		Project Costs are always operating funds.

38.	Value Management. Value Management is an organized effort directed at analyzing the 
	functions of systems, equipment, facilities, services, and supplies for achieving the 
	essential functions at the lowest life cycle cost consistent with required performance, 
	quality, reliability, and safety. Value Management encompasses Value Engineering.

39.	Value Engineering. Value Engineering is a planned, detailed review/evaluation of a 
	project to identify alternative approaches to providing the needed assets.

40.	Value Study. Value Study is an intensive review of requirements and the development 
	of alternatives by the use of appropriate value techniques utilizing aspects of 
	engineering, requirements analysis, the behavioral sciences, creativity, economic 
	analysis, and the scientific method.

41.	Variance. A variance is a deviation from the approved scope, cost, or schedule 
	performance. Variances must be tracked and reported. Variances should be mitigated 
	through corrective actions and not eliminated through baseline change control unless 
	valid rationale can be presented to justify a change in baseline. Baseline changes are 
	submitted for changes in technical, work scope, funding, or directed changes. 
	


U.S. Department of Energy					PAGE CHANGE
Washington, D.C. 					DOE O 413.3A Chg 1

							Approved:  7-28-06-08

							Chg 1:  11-17-08

SUBJECT:	PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF 
		CAPITAL ASSETS 

1.	PURPOSE.  To transmit revised pages to DOE O 413.3A, Program and Project 
	Management for the Acquisition of Capital Assets, dated 7-28-06.

2.	EXPLANATION OF CHANGES.  To incorporate the requirements of DOE-STD-1189-
	2008, Integration of Safety into the Design Process, mandatory for Hazard Category 1, 2 
	and 3 nuclear facilities into the directive.  

3.	LOCATION OF CHANGES.

Pages			Paragraphs

2			3a, 3c(1) and 4

11-13 and 15-17		Table 2

28			5k(4)

36-37			6c(13)

40			6i and 6i(2)

41			6i(5)

45			6q(8)

47			7x

Attachment 1		All

Attachment 2, 		page 2-3	

After filing the attached pages, this transmittal may be discarded.

BY ORDER OF THE SECRETARY OF ENERGY:



	JEFFREY F. KUPFER

	Acting Deputy Secretary